Work Profile Report [83W18]

एन0एच0ओ0 के अन्तर्गत वर्ष 2022-23 में रा0मा0 संख्या 87 विस्तार (नया-109) में प्रतिधारक दीवारों का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Ranikhet/01 (C. No. 212888) Dt. 30-03-2023 (Job No.RO/UK/AP/NH-87(Ext) (New 109)/2022-23/660)

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

212.00

Resanction Cost :

212.00

Tentative Cost :

212.00

Exp. Upto Last Fy :

34.70

For CFY 2024-2025

Remaining :

177.30

Demand :

80.00

Allotment :

35.44

Exp in CFY :

35.44

Total Up to Date Exp :

70.14

Construction Started

Sanction on : 1 year 4 months ago

30 Mar 2023

Physical Progress:

At start of FY 2024-2025 :

47 %

Up to Date :

72 %

Tentative Completion date on : 3 months 2 days ago

14 May 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
0.688
0.688
0.322
0.366
0.366
0.086

Remark

view all

कुल 688 रनिंग मी0 दीवार के सापेक्ष 408 रनिंग मी0 दीवार निर्माण का कार्य पूर्ण, कल्वर्ट 1 नं0 के सापेक्ष 1 नं0 पूर्ण, पैरापिट 92 नं0 के सापेक्ष 39 नं0 पूर्ण एवं एच0 रेलिंग 36 नं0 के सापेक्ष 36 नं0 पूर्ण शेष कार्य प्रगति पर। -- as on 31-Jul-2024

Rating : 72

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: