Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 45 | 45 | 0.000 | 45 | 22.000 | 25.000 |
83W20 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : F.No. NH-15017/74/2023-P&M Dt. 07-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
499.72
Resanction Cost :
499.72
Tentative Cost :
499.72
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 499.72
Demand : 200.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 58 %
Sanction on :
7 months 1 week ago
07 Dec 2023
Tentative Completion date:
7 months 3 weeks from now
11 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 31-May-2024
Physical Peramenters