Work Profile Report [83W20]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : F.No. NH-15017/74/2023-P&M Dt. 07-12-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
499.72
Resanction Cost :
499.72
Tentative Cost :
499.72
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
499.72
Demand :
350.00
Allotment :
204.20
Exp in CFY :
204.20
Total Up to Date Exp :
204.20
Construction Started
Sanction on : 1 year 2 weeks ago
07 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
67 %
Tentative Completion date on : 2 months 2 weeks from now
11 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
34 किमी0 तक बी0सी0 कार्य पूर्ण एवं 10 ंन0 काॅजवे का कार्य पूर्ण। 450 नं0 पैरापिटों में पेटिंग का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 03-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand