Work Profile Report [83W4]

Closed Work राष्ट्रीय राजमार्ग संख्या 87 विस्तार (नया 109 के किमी0 89.00 से किमी0 101.00 एवं 108.50 से 120.00 तक सुदृढ़ीकरण तथा सड़क सुरक्षा का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/12014/80/Annual Plan/2019-20 Date 19-02-2020

TS Amount (lakhs) : 1379.45 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

1379.45

Resanction Cost :

1379.45

Tentative Cost :

1379.45

Exp. Upto Last Fy :

825.98

For CFY 2024-2025

Remaining :

553.47

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

825.98

Work completed

Sanction on : 4 years 9 months ago

19 Feb 2020

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 3 years 1 week ago

15 Nov 2021

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
23.5
23.5
23.5
-

Remark

view all

Work completed. -- as on 03-Apr-2022

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck :

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Khachar Bridge Local Nala sunoli