राष्ट्रीय राजमार्ग संख्या 309 (बी) के किमी0 47.00 से किमी0 77.00 तक सड़क सुरक्षा का कार्य।


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Khanigad Steel Girder Bridge

Administrative Approval Detail : RO/UK/12014/117/Annual Plan/2019-20 Date 31-03-2020

TS Amount (lakhs) : 438.4 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

438.40

Resanction Cost :

438.40

Tentative Cost :

438.40

Exp. Upto Last Fy : 328.91

For CFY 2024-2025

Remaining : 109.49

Demand : 0.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 328.91

Work completed

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 100 %

Sanction on :
4 years 3 months ago
31 Mar 2020


Tentative Completion date:
3 years 2 months ago
28 Apr 2021


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck:


Work completed. -- as on 02-Aug-2021

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 1 0
Currently only Bank Gaurantee information is avilable