Work Profile Report [8W104]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 1220/।।।(2)/19-04(एम0एल0ए0)/2017 टीसी दि0 05.03.2019
TS Amount (lakhs) : 148.94 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
148.94
Resanction Cost :
148.94
Tentative Cost :
148.94
Exp. Upto Last Fy :
134.76
For CFY 2024-2025
Remaining :
14.18
Demand :
14.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
134.76
Work completed
Sanction on : 5 years 5 months ago
05 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 months 2 weeks from now
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दाईत्व शेष। -- as on 05-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: