Work Profile Report [8W160]

fनजमूला-पाणा मोटर मार्ग से गौैंणा भनाली तक fलंक मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities
  • alerts

    Documents

Administrative Approval Detail : शा0सं0 7075/।।।(2)/13-41 (प्रा0आ0)/2013 दि॰ 20.12.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

84.24

Resanction Cost :

84.24

Tentative Cost :

84.24

Exp. Upto Last Fy :

27.14

For CFY 2024-2025

Remaining :

57.10

Demand :

35.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

27.14

in Tendering Stage

Sanction on : 10 years 7 months ago

20 Dec 2013

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 4 months ago

31 Mar 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
4
-
Bridge
1 (90m)
1 (90m)
1 (90m)
-

Remark

view all

अपर सचिव, उत्तराखण्ड शासन के प0 360/एक्स-3-22/1(54)/ 2018 दि॰ 26.04.22 द्वारा 1.855 हे0 वनभूमि की विधिवत स्वीकृति प्राप्त।
1.32 किमी॰ मोटर मार्ग के द्वितीय चरण की स्वीकृति के सापेक्ष कार्य पूर्ण। सेतु के स्थल चयन एवं अवशेष मोटर मार्ग निर्माण की डी॰पी॰आर॰ गठन की कार्यवाही की जा रही हैै।
-- as on 30-Dec-2023

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: