Work Profile Report [8W161]

गोपेश्वर मंदिर मार्ग से वैतरणी-सिरोखोमा-सेटुंणा-बैरागना मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents

Administrative Approval Detail : शा0सं0 7075/।।।(2)/13-41 (प्रा0आ0)/2013 दि॰ 20.12.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

106.38

Resanction Cost :

106.38

Tentative Cost :

45.00

Saving

61.38

Exp. Upto Last Fy :

31.63

For CFY 2024-2025

Remaining :

74.75

Demand :

15.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

31.63

Alignment Approved

Sanction on : 10 years 7 months ago

20 Dec 2013

Physical Progress:

At start of FY 2024-2025 :

95 %

Up to Date :

70 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

Overall Saving 61.38 has been recorded as expected cost of work reduced from 106.38 to 45 . Remaining amount of compotation only. Botle neck for compensation distribution of ST land. -- as on 24-Jul-2024

Rating : 79

Forest Case Pending At : 12: AIP DM

Hindrance / Bottleneck : Compensation Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: