Work Profile Report [8W170]

वणद्वारा से काण्डई तक मोटर मार्ग का निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 5150/।।।(2)/10-18 (प्रा0आ0)/2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

37.80

Resanction Cost :

37.80

Tentative Cost :

37.80

Exp. Upto Last Fy :

10.75

For CFY 2024-2025

Remaining :

27.05

Demand :

15.00

Allotment :

20.00

Exp in CFY :

0.00

Total Up to Date Exp :

10.75

Alignment Approved

Sanction on : 14 years 4 months ago

16 Aug 2010

Physical Progress:

At start of FY 2024-2025 :

75 %

Up to Date :

75 %

Tentative Completion date on : 1 month 3 weeks ago

31 Oct 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
3
-

Remark

view all

अवशेष धनराशि से मुआवजा भुगतान किया जiना है। -- as on 24-Jul-2024

Rating : 75

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand