Work Profile Report [8W223]

जनपद चमोली के विकासखण्ड दशोली में डुंगरी से कुंज पोथनी-बौंला मोटर मार्ग मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities
  • alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 1648/।।।(2)/13-52(प्रा0आ0)/2012 दिनांक 04.03.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

125.80

Resanction Cost :

125.80

Tentative Cost :

49.37

Saving

76.43

Exp. Upto Last Fy :

8.51

For CFY 2025-2026

Remaining :

117.29

Demand :

10.00

Allotment :

4.24

Exp in CFY :

4.24

Total Up to Date Exp :

12.76

Alignment Approved

Sanction on : 12 years 10 months ago

04 Mar 2013

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

60 %

Tentative Completion date on : 1 year 2 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

वर्तमान में पहाड़ कटान का कार्य प्रगति पर है। तत्पश्चात निर्माण से प्रभावित कास्तकारों को नापभूमि प्रतिकर भुगतान किया जाना है। -- as on 12-Jan-2026

Rating : 60

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© 2026 PWD Uttarakhand