Work Profile Report [8W225]

मा0मुख्यमंत्री घोषणा संख्या 40/2019 के अन्तर्गत जनपद चमोली के विकासखण्ड दशोली में बछेरधार से बछेर गांव तक विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 1971(1)/।।।(2)/13-52(प्रा0आ0) /2012 दिनांक 14.03.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.32

Resanction Cost :

50.32

Tentative Cost :

50.32

Exp. Upto Last Fy :

47.13

For CFY 2024-2025

Remaining :

3.19

Demand :

3.19

Allotment :

3.00

Exp in CFY :

3.00

Total Up to Date Exp :

50.13

Work completed

Sanction on : 11 years 9 months ago

14 Mar 2013

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

100 %

Tentative Completion date on : 1 month 3 weeks ago

31 Oct 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000

Remark

view all

सम्मस्त कार्य पूर्ण। -- as on 28-Oct-2024

Rating : 100

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: