Work Profile Report [8W28]

पातालगंगा से गणाई -मोल्टा तक 10 किमी॰ एवं किमी॰ 5 पर 2 (40 मी॰, 30 मी॰) एवं किमी॰ 8 पर 2 (25 मी॰, 20 मी॰) मोटर सेतु

    Tenders

    Aggrements

    alerts

    Samples

Administrative Approval Detail : 3431/।।।-2/06-56 (प्रा॰आ॰)/06 दि॰ 22.12.06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

493.95

Resanction Cost :

493.95

Tentative Cost :

493.95

Exp. Upto Last Fy :

3.08

For CFY 2025-2026

Remaining :

490.87

Demand :

220.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.08

Alignment Approved

Sanction on : 18 years 3 months ago

22 Dec 2006

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

10 %

Tentative Completion date on : 2 months 2 weeks from now

30 Jun 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
10
-
Bridge
4 (115m)
4 (115m)
4 (115m)
-

Remark

view all

1- भारत सरकार के पत्रांक 8B/UCP/06/71/2021/FC/1271 दि॰ 23.12.2022 द्वारा सैद्धान्तिक स्वीकृति प्राप्त।
2- मुख्य अभियन्ता, लो0नि0वि0, पौड़ी के पत्रांे 5120/07 सामान्य (पार्ट-1)-पौड़ी/2024 दि० 13.09.2024 द्वारा गठित समिति द्वारा दि० 10.12.2024 को पुनः स्थल का भूगर्भीय निरीक्षण किया गया, जिसमें मात्र 3.00 किमी० लम्बाई में ही स्थल को मोटर मार्ग निर्माण हेतु उपयुक्त बताया गया। जिसके क्रम में 3.00 किमी0 लम्बाई के संरेखण प्रस्ताव पर अधीक्षण अभियन्ता, लो0नि0वि0, गोपेश्वर के पत्रांक 469/485 याता-7/2023 दि0 04.02.2025 द्वारा अनमंादन प्राप्त कर लिया गया है। वर्तमान में मार्ग निर्माण का आगणन, लागत रु0 245.43 लाख प्राविधिक स्वीकृति हेतु प्रेषित।
प्रभागीय वनाधिकारी, बद्रीनाथ वन प्रभाग, गोपेश्वर से कार्य प्रारम्भ करने हेतु अनुमति प्राप्त करने की कार्यवाही गतिमान है।
-- as on 25-Mar-2025

Rating : 10

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck