Work Profile Report [8W295]
Tenders
Project Activities
alerts
Administrative Approval Detail : GO No 5254(1)/III(2)/21-04(MLA)/2017 TC III
TS Amount (lakhs) : 192.04 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
192.04
Resanction Cost :
205.37
Tentative Cost :
205.37
Exp. Upto Last Fy :
173.69
For CFY 2024-2025
Remaining :
31.68
Demand :
18.35
Allotment :
16.68
Exp in CFY :
7.53
Total Up to Date Exp :
181.22
Construction Started
Sanction on : 2 years 9 months ago
30 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
74 %
Up to Date :
89 %
Tentative Completion date on : 2 months 4 weeks from now
15 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress. Bad weather and ongoing yatra hindering work progress. -- as on 26-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: