Work Profile Report [8W297]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO No 6439/III(2)/21-04(PRA. AA.)/2017 TC III
TS Amount (lakhs) : 94.18 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.18
Resanction Cost :
94.18
Tentative Cost :
94.18
Exp. Upto Last Fy :
72.48
For CFY 2024-2025
Remaining :
21.70
Demand :
5.00
Allotment :
21.70
Exp in CFY :
0.00
Total Up to Date Exp :
72.48
Construction Started
Sanction on : 3 years 2 days ago
23 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
54 %
Up to Date :
54 %
Tentative Completion date on : 6 months 4 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 25-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand