Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.77 | 15.77 | 0.000 | 15.77 | 0.000 | 0.000 |
8W298 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO No- 1701/III(2)/22-04(M.L.A.)/2017 TC III
TS Amount (lakhs) : 396.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
396.13
Resanction Cost :
421.78
Tentative Cost :
421.78
Exp. Upto Last Fy : 264.55
For CFY 2024-2025
Remaining : 157.23
Demand : 131.58
Allotment : 0.33
Exp in CFY : 0.33
Total Up to Date Exp : 264.88
Current Liability: 0.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 72 %
Up to Date : 82 %
Sanction on :
2 years 3 months ago
29 Mar 2022
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
कार्य प्रगति पर है। -- as on 07-Jun-2024
Physical Peramenters