Work Profile Report [8W298]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : GO No- 1701/III(2)/22-04(M.L.A.)/2017 TC III
TS Amount (lakhs) : 396.13 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
396.13
Resanction Cost :
421.78
Tentative Cost :
310.00
Saving
111.78
Exp. Upto Last Fy :
264.55
For CFY 2024-2025
Remaining :
157.23
Demand :
37.08
Allotment :
71.33
Exp in CFY :
17.08
Total Up to Date Exp :
281.63
Current Liability:
0.33
Construction Started
Sanction on : 2 years 7 months ago
29 Mar 2022
Physical Progress:
At start of FY 2024-2025 :
72 %
Up to Date :
82 %
Tentative Completion date on : 1 week 1 day ago
15 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Final measurement to be done. Few HP bends not able to be cut due to extreme hieght of cutting and continous yatra during fair weather. Rest of the time, extreme weather conditions exist at site. -- as on 09-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand