Work Profile Report [8W30]

एस॰सी॰पी॰ के अन्तर्गत कुहेड़ - मैठाणा - पलेठी हल्का वाहन मार्ग से ग्राम मथरपाल - नैथेली तक मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 830/।।।-2/08-29 (प्रा॰आ॰)/07 दि॰ 24.03.08

TS Amount (lakhs) : 789.79 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

813.70

Resanction Cost :

813.70

Tentative Cost :

585.66

Saving

228.04

Exp. Upto Last Fy :

588.09

For CFY 2025-2026

Remaining :

225.61

Demand :

11.00

Allotment :

7.41

Exp in CFY :

0.00

Total Up to Date Exp :

588.09

Work completed

Sanction on : 17 years 1 week ago

24 Mar 2008

Physical Progress:

At start of FY 2025-2026 :

90 %

Up to Date :

100 %

Tentative Completion date on : 3 years 6 days ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
30
11.47
11.47
-

Remark

view all

प्रथम 5.75 किमी॰ में पी॰एम॰जी॰एस॰वाई॰ द्वारा कार्य किया जा रहा है। शेष 11.47 किमी॰ में पहाड़ कटान का कार्य पूर्ण कर लिया गया है। स्कपर दीवारों का निर्माण कार्य पूर्ण। वर्तमान में पी.एम.जी.एस.वाई. द्वारा डामरीकरण एवं सुदृढ़ीकरण का कार्य पूर्ण कर लिया गया है। -- as on 09-Nov-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: