Work Profile Report [8W301]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : GO No- 426(1)/III(2)/22-04(M.L.A.)/2017 TCI
TS Amount (lakhs) : 234.05 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
234.05
Resanction Cost :
248.05
Tentative Cost :
244.03
Saving
4.02
Exp. Upto Last Fy :
235.85
For CFY 2025-2026
Remaining :
12.20
Demand :
3.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
235.85
In Maintenance After Completion
Sanction on : 4 years 2 weeks ago
05 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 6 months ago
29 Jun 2023
Actual Completion Date : 2 years 6 months ago
28 Jun 2023
Physical Linear Components
Remark
Overall Saving 4.02 has been recorded as expected cost of work reduced from 248.05 to 244.03 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: