Work Profile Report [8W39]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 1956/।।।(2)/20-04(एम.एल.ए.)/2017 टी.सी.। दि0 23.10.2020
TS Amount (lakhs) : 363.61 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
204.17
Resanction Cost :
217.95
Tentative Cost :
217.95
Exp. Upto Last Fy :
201.78
For CFY 2024-2025
Remaining :
16.17
Demand :
4.60
Allotment :
0.00
Exp in CFY :
0.08
Total Up to Date Exp :
201.87
In Maintenance After Completion
Sanction on : 3 years 9 months ago
23 Oct 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 2 weeks ago
30 Sep 2023
Actual Completion Date : 1 year 4 months ago
31 Mar 2023
Physical Linear Components
Remark
कार्य पूर्ण। वर्तमान में डी0 एल0 पी0 अवधि में है। -- as on 07-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: