Work Profile Report [8W391]
Tenders
alerts
Documents
Samples
Administrative Approval Detail : शा0 ई0 फाइल सं0. 36696 लो0नि0 अनुभाग-2 दि0 11.05.2023
TS Amount (lakhs) : 235.38 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
235.38
Resanction Cost :
235.38
Tentative Cost :
235.38
Exp. Upto Last Fy :
142.54
For CFY 2024-2025
Remaining :
92.84
Demand :
91.83
Allotment :
57.05
Exp in CFY :
57.05
Total Up to Date Exp :
199.60
Construction Started
Sanction on : 1 year 7 months ago
11 May 2023
Physical Progress:
At start of FY 2024-2025 :
74 %
Up to Date :
74 %
Tentative Completion date on : 4 months 2 weeks from now
10 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.20 किमी0 लम्बाई में पहाड कटान पूर्ण। शेष लम्बाई में कार्य प्रगति में है। -- as on 07-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: