Work Profile Report [8W392]
Tenders
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई-फाईल सं॰ 37619 लो0नि0अनु0-2 दि॰ 19.05.2023
TS Amount (lakhs) : 55.99 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
55.99
Resanction Cost :
55.99
Tentative Cost :
55.99
Exp. Upto Last Fy :
31.70
For CFY 2024-2025
Remaining :
24.29
Demand :
23.92
Allotment :
17.92
Exp in CFY :
17.92
Total Up to Date Exp :
49.62
Construction Started
Sanction on : 1 year 7 months ago
19 May 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
75 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड कटान कार्य प्रगति पर है। -- as on 07-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: