Work Profile Report [8W435]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा सं0 164441/2023 ई फाइल सं0 35599 लोक निर्माण अनुभाग-2 दि0 26.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
45.77
Resanction Cost :
45.77
Tentative Cost :
45.77
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
45.77
Demand :
45.77
Allotment :
0.00
Exp in CFY :
19.65
Total Up to Date Exp :
19.65
Survey work done
Sanction on : 9 months 3 weeks ago
26 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
15 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 25-Jul-2024