Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
8W438 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा सं0 164903/2023 ई फाइल सं0 63230 लोक निर्माण अनुभाग-2 दि0 27.10.2023
TS Amount (lakhs) : 146.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
146.91
Resanction Cost :
146.91
Tentative Cost :
146.91
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 146.81
Demand : 100.00
Allotment : 50.00
Exp in CFY : 48.91
Total Up to Date Exp : 49.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 59 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
1 year 1 week from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्टोन सेट पेवमेंट एवं रेलिंग लगाने का कार्य प्रगति पर है। -- as on 10-Jun-2024
Physical Peramenters