Work Profile Report [8W440]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0सं0 4088/III(2) /2023-(प्रा0 आ0)/2023
TS Amount (lakhs) : 288.17 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
288.17
Resanction Cost :
288.17
Tentative Cost :
288.17
Exp. Upto Last Fy :
152.87
For CFY 2024-2025
Remaining :
135.30
Demand :
86.78
Allotment :
90.00
Exp in CFY :
76.78
Total Up to Date Exp :
229.65
Construction Started
Sanction on : 1 year 1 month ago
01 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
75 %
Tentative Completion date on : 1 month 2 weeks ago
11 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 11-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: