Work Profile Report [8W476]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश ई-फाईल सं॰ 48456/लो0नि0 अनु-2 दि॰ 30.01.2024
TS Amount (lakhs) : 160.09 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
160.09
Resanction Cost :
160.09
Tentative Cost :
160.09
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
160.09
Demand :
160.09
Allotment :
70.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 9 months 3 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
15 %
Tentative Completion date on : 7 months 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण कार्य पूर्ण, पी0सी0 कार्य प्रगति पर है। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: