Work Profile Report [8W508]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 264/III(3) /2024-01(CRIF)2024 PWD SECTION -3
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1043.62
Resanction Cost :
1043.62
Tentative Cost :
1043.62
Exp. Upto Last Fy :
985.97
For CFY 2025-2026
Remaining :
57.65
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
985.97
Construction Started
Sanction on : 1 year 9 months ago
12 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
79 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 57.65 has been counted as tentative cost increased from 985.97 to 1043.62 . -- as on 12-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: