Work Profile Report [8W510]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-35061 दिनांक 06.08.2024
TS Amount (lakhs) : 110.73 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
110.73
Resanction Cost :
118.21
Tentative Cost :
110.17
Saving
8.04
Exp. Upto Last Fy :
63.08
For CFY 2025-2026
Remaining :
55.13
Demand :
46.09
Allotment :
46.09
Exp in CFY :
46.09
Total Up to Date Exp :
109.17
Work completed
Sanction on : 1 year 5 months ago
06 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
30 May 2025
Actual Completion Date : 8 months 2 weeks ago
06 May 2025
Physical Linear Components
Remark
Overall Saving 8.04 has been recorded as expected cost of work reduced from 118.21 to 110.17 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: