Work Profile Report [8W93]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 5029/।।।(2)/18-04(एम0एल0ए0)/2017 दि0 11.10.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.60
Resanction Cost :
98.60
Tentative Cost :
98.60
Exp. Upto Last Fy :
9.43
For CFY 2024-2025
Remaining :
89.17
Demand :
73.62
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.43
Work completed
Sanction on : 5 years 10 months ago
11 Oct 2018
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
25 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Compensation distribution remaining. -- as on 25-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: