Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12.5 | 12.5 | 7.000 | 5.5 | 0.000 | 0.000 |
9W177 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 725/।।।(2)/14-56(प्रा0आ0)/2013 दिं0 08.02.2014
TS Amount (lakhs) : 328.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
328.30
Resanction Cost :
328.30
Tentative Cost :
328.30
Exp. Upto Last Fy : 210.77
For CFY 2024-2025
Remaining : 117.53
Demand : 20.00
Allotment : 0.00
Exp in CFY : 5.16
Total Up to Date Exp : 215.93
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 70 %
Sanction on :
10 years 5 months ago
08 Feb 2014
Tentative Completion date:
11 months 1 week from now
30 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
स्वीकृत कार्य के अन्तर्गत नैनीताल शहर के महत्वपूर्ण ट्रैकिंग मार्गो का कार्य किया जाना प्रस्तावित है। जिसके सापेक्ष 11 ट्रैकिंग मार्गो का सुधारीकरण का कार्य पूर्ण कर लिया गया है। एक मात्र नैनीताल अल्मोड़ा पैदल मार्ग का सुधारीकरण का कार्य किया जाना है। उक्त मार्ग कैन्ट ऐरिया मे होने के कारण मुख्य कार्यकारी अधिकारी कैन्ट बोर्ड से सम्पर्क किया गया तथा उनके द्वारा भू-वैज्ञानिक से निरीक्षण करा कर निरीक्षण के आधार पर कार्य कराने हेतु अवगत कराया गया है। जिसके क्रम में भू-वैज्ञानिक द्वारा मार्ग का निरीक्षण किया जा चुका है आख्या आपेक्षित है। आख्या प्राप्त होने के उपरानत ही मार्ग के सुधारीकरण का कार्य किया जा सकेगा। -- as on 13-Jul-2024
Physical Peramenters