Work Profile Report [9W224]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 7662/।।।(2)/15-22 (प्रा0आ0)/ 2004 दिं0 11.03.2016
TS Amount (lakhs) : 498.58 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
498.58
Resanction Cost :
498.58
Tentative Cost :
498.58
Exp. Upto Last Fy :
489.63
For CFY 2024-2025
Remaining :
8.95
Demand :
8.95
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
489.63
Work completed
Sanction on : 8 years 8 months ago
11 Mar 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 3 weeks ago
31 Oct 2020
Actual Completion Date : 5 years 5 months ago
01 Jun 2019
Physical Linear Components
Remark
बी0एम0एस0डी0बी0सी0 का कार्य पूर्ण। परन्तु ई0ओ0टी0 / विचलन सक्षम स्तर से अनुमोदित होना है। अंतिम देयक भुगतान हेतु प्रस्तुत। -- as on 30-Nov-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand