Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 20 | 20 | 20 | 0 |
9W380 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file No 47018 / Lok Nirman Anubagh - 2 dt 14-02-2023
TS Amount (lakhs) : 6.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.20
Resanction Cost :
6.20
Tentative Cost :
6.20
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 6.20
Demand : 6.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
1 year 5 months ago
14 Feb 2023
Tentative Completion date:
2 months 1 week ago
04 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जयो टेक्निकल टेस्ट हेतु निविदा प्राप्त कर कार्य प्रगति पर है। -- as on 09-Jul-2024
Physical Peramenters