Work Profile Report [9W397]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File no 47917 lok niman aubhad 2 dt. 25-09-2023
TS Amount (lakhs) : 53.55 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.55
Resanction Cost :
53.55
Tentative Cost :
53.55
Exp. Upto Last Fy :
12.24
For CFY 2024-2025
Remaining :
41.31
Demand :
41.31
Allotment :
40.00
Exp in CFY :
31.82
Total Up to Date Exp :
44.05
Construction Started
Sanction on : 1 year 3 months ago
25 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
95 %
Tentative Completion date on : 4 months 1 week ago
15 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग मे कर्लवट, डामरीकरण व इन्टर लाकिंग का कार्य पूर्ण। नाली एवं पैरापिट निर्माण कार्य प्रगति पर। -- as on 26-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: