Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.28 | 7.28 | 0.000 | 7.28 | 7.280 | 0.000 |
9W418 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No 48456/ Lok Niman Anubagh-2 dt. 30.01.2024
TS Amount (lakhs) : 149.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
149.13
Resanction Cost :
149.13
Tentative Cost :
149.13
Exp. Upto Last Fy : 10.03
For CFY 2024-2025
Remaining : 139.10
Demand : 139.10
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
4 months 2 weeks from now
04 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्कपरो एवं पैरापिटो का निर्माण कार्य पूर्ण दीवारो का निर्माण कार्य प्रगति पर । -- as on 18-Jun-2024
Physical Peramenters