Work Profile Report [9W422]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : E File No 61203 LN Anubagh - 2 dt 30-10-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.32
Resanction Cost :
9.32
Tentative Cost :
9.32
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
9.22
Demand :
9.22
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Construction Started
Sanction on : 9 months 2 weeks ago
30 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 1 week 23 hours from now
24 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जयो टेक्निकल टेस्ट हेतु निविदा प्राप्त कर कार्य प्रगति पर है। -- as on 09-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: