Work Profile Report [9W573]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी नैनीताल का पत्रांक 548/ बजट आवटन/जि0यो0/स्वी0/ लो0नि0वि0/25-32/ 2024-25 दिं0 27.08.24
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
3.00
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.00
Work completed
Sanction on : 10 months 3 weeks ago
27 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
04 Mar 2025
Actual Completion Date : 4 months 2 weeks ago
28 Feb 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 12-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: