Administrative Approval Detail : शा0सं0 1271/(1)/।।।(2)/21-संशोधित -58 (एम0एल0ए0)/2017
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
269.73
Resanction Cost :
269.73
Tentative Cost :
269.73
Exp. Upto Last Fy :
268.14
For CFY 2025-2026
Remaining :
1.59
Demand :
0.00
Allotment :
0.19
Exp in CFY :
0.19
Total Up to Date Exp :
268.33
In Maintenance After Completion
Sanction on : 4 years 1 month ago
19 Apr 2021
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
100 %
Tentative Completion date on : 2 years 1 month ago
31 Mar 2023
Actual Completion Date : 2 years 5 months ago
20 Dec 2022
Physical Linear Components
Remark
कार्य पूर्ण माह 12/2022 में पूर्ण -- as on 08-Sep-2023