Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16 | 10.52 | 10.520 | 0 | 0.000 | 0.000 |
10W14 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2454/।।। (2)/05-07 (प्रा0आ0)/05 दि0 28/10/05शा0सं0 7001/।।। (2)/18-32 (प्रा0आ0)/2017 दि0 17/12/18
TS Amount (lakhs) : 600.98 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
222.40
Resanction Cost :
600.98
Tentative Cost :
600.98
Exp. Upto Last Fy : 528.14
For CFY 2024-2025
Remaining : 72.84
Demand : 2.00
Allotment : 2.00
Exp in CFY : 0.00
Total Up to Date Exp : 528.14
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 8 months ago
28 Oct 2005
Tentative Completion date:
8 months 3 weeks ago
22 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, अनुरक्षण का कार्य प्रगति पर है। -- as on 04-Jul-2024
Physical Peramenters