Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.700 | 2.3 | 0.000 | 0.000 |
10W24 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2555/।।।- (2)/06-41 (प्रा0आ0)/06 दि0 26/9/06 एवं पुनरीक्षित स्वीकृति शा0सं0 876/।।।(2)/21-40 (प्रा0आ0)/2006 टी0सी0 दिं0 25.03.2021 द्वारा लागत रू0 264.75 लाख की प्राप्त।
TS Amount (lakhs) : 264.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.00
Resanction Cost :
264.75
Tentative Cost :
264.75
Exp. Upto Last Fy : 222.00
For CFY 2024-2025
Remaining : 42.75
Demand : 20.00
Allotment : 12.19
Exp in CFY : 12.50
Total Up to Date Exp : 234.50
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 9 months ago
26 Sep 2006
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा वितरण की कार्यवाही की जा रही है। -- as on 19-Feb-2024
Physical Peramenters