Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 1.500 | 2.5 | 0.000 | 0.000 |
10W292 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 561/।।। (2) /19-57 (एम.एल.ए.)/2016 टी0सी0 दिनाॅक 4.2.2019
TS Amount (lakhs) : 253 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
253.00
Resanction Cost :
253.00
Tentative Cost :
253.00
Exp. Upto Last Fy : 181.79
For CFY 2024-2025
Remaining : 71.21
Demand : 1.00
Allotment : 1.00
Exp in CFY : 0.00
Total Up to Date Exp : 181.79
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
04 Feb 2019
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, अनुरक्षण का कार्य प्रगति पर है। -- as on 04-Jul-2024
Physical Peramenters