Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.000 | 2 | 2.000 | 0.000 |
10W30 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0547/।।।- (2)/09-44 (प्रा0आ0) /08 दि0 11/2/09
TS Amount (lakhs) : 105 Lacs
Financial Detail
Sanction Cost : 105.00 Lacs
Resanction Cost : 105.00 Lacs
Exp. Upto Last Fy : 72.09 Lacs
For CFY 2024-2025
Remaining : 32.91 Lacs
Demand : 32.91 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 72.09 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
15 years 3 months ago
11 Feb 2009
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण, पार्ट-।। का कार्य कराया जाना है। -- as on 20-Feb-2024
Physical Peramenters