Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.000 | 2 | 2.000 | 0.000 |
10W30 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0547/।।।- (2)/09-44 (प्रा0आ0) /08 दि0 11/2/09
TS Amount (lakhs) : 105 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy : 72.09
For CFY 2024-2025
Remaining : 32.91
Demand : 32.91
Allotment : 7.02
Exp in CFY : 7.01
Total Up to Date Exp : 79.10
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
15 years 5 months ago
11 Feb 2009
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 कि0मी0 लम्बाई में पहाड़ कटान एवं 1.00 कि0मी0 लम्बाई में पार्ट-।। का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 03-Jun-2024
Physical Peramenters