Work Profile Report [10W327]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1348/।।।(2)/20-58 (एम0एल0ए0)/2017टी0सी0।।। दिं0 23.07.2020
TS Amount (lakhs) : 94.72 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.72
Resanction Cost :
94.72
Tentative Cost :
92.52
Saving
2.20
Exp. Upto Last Fy :
86.97
For CFY 2024-2025
Remaining :
7.75
Demand :
1.00
Allotment :
1.00
Exp in CFY :
0.00
Total Up to Date Exp :
86.97
In Maintenance After Completion
Sanction on : 4 years 5 months ago
23 Jul 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 8 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुरक्षण का कार्य किया जा रहा है। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand