Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.500 | 0 | 0.000 | 0.000 |
10W346 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6032(1)/III(2)/21-57(MLA) 2017 T.C.
TS Amount (lakhs) : 99.05 Lacs
Financial Detail
Sanction Cost : 99.05 Lacs
Resanction Cost : 99.05 Lacs
Exp. Upto Last Fy : 90.29 Lacs
For CFY 2024-2025
Remaining : 8.76 Lacs
Demand : 0.60 Lacs
Allotment : 0.60 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 90.29 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 5 months ago
11 Dec 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
4 months 3 weeks ago
28 Dec 2023
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 13-Oct-2023
Physical Peramenters