Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
10W355 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/38/2023-III-2-PUBLIC WORKS DEPARTMENT /133114/2023
TS Amount (lakhs) : 71.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
71.57
Resanction Cost :
71.57
Tentative Cost :
71.57
Exp. Upto Last Fy : 43.60
For CFY 2024-2025
Remaining : 27.97
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.07
Total Up to Date Exp : 43.67
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 3 weeks ago
26 Jun 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
1.50 कि0मी0 लम्बाई में पहाड़ कटान पूर्ण, उससे आगे विवाद हो जाने के कारण कार्य बाधित है। -- as on 19-Feb-2024