Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.75 | 9.75 | 0.000 | 9.75 | 9.750 | 7.500 |
10W359 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन, देहरादून का ई-फाईल संख्या 44081
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
166.43
Resanction Cost :
166.43
Tentative Cost :
166.43
Exp. Upto Last Fy : 21.00
For CFY 2024-2025
Remaining : 145.43
Demand : 130.00
Allotment : 97.73
Exp in CFY : 94.40
Total Up to Date Exp : 115.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 65 %
Sanction on :
9 months 2 weeks ago
03 Oct 2023
Tentative Completion date:
4 months 1 week from now
29 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
7.50 किमी ० लम्बाई में पीसी का कार्य पूर्ण शेष कार्य प्रगति में । -- as on 29-Jun-2024
Physical Peramenters