Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.75 | 9.75 | 0.000 | 9.75 | 9.750 | 2.750 |
10W359 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन, देहरादून का ई-फाईल संख्या 44081
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 166.43 Lacs
Resanction Cost : 166.43 Lacs
Exp. Upto Last Fy : 21.00 Lacs
For CFY 2024-2025
Remaining : 145.43 Lacs
Demand : 130.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 32.72 Lacs
Total Up to Date Exp : 53.72 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 30 %
Sanction on :
7 months 2 weeks ago
03 Oct 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.75 किमी ० लम्बाई में पीसी का कार्य पूर्ण शेष कार्य प्रगति में । -- as on 06-May-2024
Physical Peramenters