Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
10W363 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला एवं अर्थ एवं संख्याधिकारी / उप सचिव जिला योजना समिति, नैनीताल का पत्रांक 703/जि0यो0/2023-24
TS Amount (lakhs) : 31.92 Lacs
Financial Detail
Sanction Cost : 31.92 Lacs
Resanction Cost : 31.92 Lacs
Exp. Upto Last Fy : 13.98 Lacs
For CFY 2024-2025
Remaining : 17.94 Lacs
Demand : 12.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 8.58 Lacs
Total Up to Date Exp : 22.56 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
8 months 2 hours ago
19 Sep 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 18-Dec-2023