Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
10W367 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4088/।।।(2)/2023- (प्रा0आ0)/2023 दिं0 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1333.93
Resanction Cost :
1333.93
Tentative Cost :
1333.93
Exp. Upto Last Fy : 70.54
For CFY 2024-2025
Remaining : 1,263.39
Demand : 1,263.39
Allotment : 735.00
Exp in CFY : 319.32
Total Up to Date Exp : 389.85
Construction Started
Physical Progress:
At start of FY 2024-2025 : 3 %
Up to Date : 52 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
1 month 3 weeks from now
09 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य के अन्तर्गत लक्ष्मीखान-तल्ला रामगढ़-नथुवाखान-प्यूड़ा-क्वारब मुख्य जिला जिला मार्ग-11 में कार्य पूर्ण किया जा चुका है।
तल्ला रामगढ़ झूतिया मोटर मार्ग में कार्य प्रगति पर है।
भुजान-बेतालघाट मोटर मार्ग में कार्य प्रगति पर है।
बेतालघाट-भतरौजखान-तौराड़ में कार्य प्रगति पर है।
-- as on 09-May-2024