Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.27 | 4.27 | 0.000 | 4.27 | 4.270 | 0.000 |
10W372 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No. 44081 dt. 18-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
251.65
Resanction Cost :
251.65
Tentative Cost :
251.65
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 251.55
Demand : 200.00
Allotment : 41.00
Exp in CFY : 21.29
Total Up to Date Exp : 21.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
6 months 4 weeks ago
18 Dec 2023
Tentative Completion date:
10 months 2 weeks from now
05 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0एस0बी0 का कार्य पूर्ण। इंटर कोट 4.20 कि0मी0 पूर्ण, शेष कार्य प्रगति पर। -- as on 29-Jun-2024
Physical Peramenters