Work Profile Report [10W376]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-File No. 44081/57 dt. 28-02-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
154.77
Resanction Cost :
154.77
Tentative Cost :
154.77
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
154.67
Demand :
136.00
Allotment :
115.67
Exp in CFY :
34.12
Total Up to Date Exp :
34.23
Construction Started
Sanction on : 8 months 3 weeks ago
28 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
35 %
Tentative Completion date on : 3 months 1 week from now
06 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0 एवं इंटर का कार्य पूर्ण। टाॅप कोट 1.00 कि0मी0 लम्बाई में पूर्ण, शेष कार्य प्रगति में। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: