Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 0.000 | 2.8 | 0.000 | 0.000 |
10W376 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No. 44081/57 dt. 28-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 154.77 Lacs
Resanction Cost : 154.77 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 154.67 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 months 3 weeks ago
28 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा आमंत्रित -- as on 06-Mar-2024
Physical Peramenters