Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 0.000 | 2.8 | 0.000 | 0.000 |
10W376 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No. 44081/57 dt. 28-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
154.77
Resanction Cost :
154.77
Tentative Cost :
154.77
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 154.67
Demand : 100.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
4 months 2 weeks ago
28 Feb 2024
Tentative Completion date:
7 months 2 weeks from now
06 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0एस0बी0 2.00 कि0मी0 में पूर्ण, शेष कार्य प्रगति में। -- as on 29-Jun-2024
Physical Peramenters