Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Span of Bridges [m] | 125 | 125 | 125 | 0 |
10W378 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/164913/2023 E-file No. 61203 dt. 30-10-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.38
Resanction Cost :
18.38
Tentative Cost :
18.38
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 18.38
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा आमंत्रित -- as on 06-Mar-2024
Physical Peramenters