Work Profile Report [10W380]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : ई0 पत्रावली संख्या-56385 दिं0 15.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
730.00
Resanction Cost :
730.00
Tentative Cost :
730.00
Exp. Upto Last Fy :
724.52
For CFY 2025-2026
Remaining :
5.48
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
724.52
Work completed
Sanction on : 1 year 5 months ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 2 weeks ago
17 May 2025
Actual Completion Date : 6 months 2 days ago
04 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand