Work Profile Report [10W48]

एस0सी0पी0 के अन्तर्गत सतोली कफुड़ा मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 827/।।।- (2)/06-76 (प्रा0आ0)/05 टी0सी0 दि0 28/3/06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

106.80

Resanction Cost :

106.80

Tentative Cost :

106.80

Exp. Upto Last Fy :

3.86

For CFY 2024-2025

Remaining :

102.94

Demand :

60.00

Allotment :

2.60

Exp in CFY :

0.00

Total Up to Date Exp :

3.86

Construction Started

Sanction on : 18 years 7 months ago

28 Mar 2006

Physical Progress:

At start of FY 2024-2025 :

15 %

Up to Date :

20 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
2
0.000
2
0.000
0.000

Remark

view all

मोटर मार्ग में 1.500 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण है।शेष कार्य प्रगति में। -- as on 24-Oct-2024

Rating : 21

Forest Case Pending At : 21: Final

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: