Work Profile Report [10W7]

जनपद नैनीताल में कूल बिरखन- सूंड मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं063/।।। (2)/05-91 (प्रा0आ0)/05 दि0 16/01/06

TS Amount (lakhs) : 71.2 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

71.20

Resanction Cost :

71.20

Tentative Cost :

71.20

Exp. Upto Last Fy :

50.32

For CFY 2024-2025

Remaining :

20.88

Demand :

20.88

Allotment :

15.00

Exp in CFY :

0.00

Total Up to Date Exp :

50.32

Construction Started

Sanction on : 18 years 11 months ago

16 Jan 2006

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

90 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
1.000
0.000

Remark

view all

वर्तमान में प्रभागीय वनाधिकारी हलद्वानी के पत्रांक 1256/12-1 हल्द्वानी दिं0 05.12.2024 द्वारा प्रकरण वन संरक्षक, पश्चिमी वृत्त, हल्द्वानी उत्तराखण्ड को प्रेषित। -- as on 21-Dec-2024

Rating : 93

Forest Case Pending At : 14: AIP Conservator

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: